Log Cabin - Day Three

Previous Topic Next Topic
 
Posted by RustonHouse RustonHouse
Options
Once again, shortly after midday, I made a trip with camera to see progress on the cabin.

Log Cabin Erection - Day Three
From a distance you really get a good idea of how it will sit in the landscape.

Log Cabin Erection - Day Three
Once at the site we see that the veranda roof, or loft floor, has been fitted...

Log Cabin Erection - Day Three
...as has that to both rooms the cabin. Both are now covered with a protective sheet while work continues.

Log Cabin Erection - Day Three
Up on the roof the team consider the next rafter to be put in position.

Log Cabin Erection - Day Three
By the end of play you'll see that the main room looks dark. Not only are all the rafters are in place but the ceilng boards are all in place and and the roof boards on the front of the cabin are there.

Log Cabin Erection - Day Three
Inside, you can now see how the area above the veranda will look. It's a substantial area, some 5m x 2m.